Inclusive Employment Australia is the federal program that helps people with disability, injury or illness find and keep work. The Department of Social Services publishes a monthly profile of it as a spreadsheet on data.gov.au. In August we read the first eight editions and said in our first look at the program that a twelve-month window entirely inside it would become possible from the November 2026 report. That report is the 31 October 2026 edition, which data.gov.au records as added on 3 November. We read every cell of it.
The year, month by month
| Month | Referrals | Commencements | Exits | 12-week outcomes | 26-week outcomes | 52-week outcomes |
|---|---|---|---|---|---|---|
| Nov 2025 | 9,740 | 8,420 | 1,845 | 925 | 910 | 565 |
| Dec 2025 | 5,905 | 5,770 | 2,495 | 1,750 | 1,425 | 850 |
| Jan 2026 | 8,080 | 8,300 | 4,290 | 1,650 | 1,855 | 880 |
| Feb 2026 | 7,595 | 7,260 | 4,370 | 1,600 | 1,710 | 1,145 |
| Mar 2026 | 9,220 | 7,430 | 4,575 | 1,825 | 2,080 | 1,455 |
| Apr 2026 | 8,205 | 6,570 | 4,345 | 2,130 | 1,510 | 1,245 |
| May 2026 | 7,575 | 6,690 | 4,995 | 3,040 | 1,350 | 1,320 |
| Jun 2026 | 7,600 | 6,700 | 4,900 | 2,945 | 1,370 | 1,415 |
| Jul 2026 | 8,270 | 7,010 | 5,090 | 2,875 | 1,490 | 1,360 |
| Aug 2026 | 8,840 | 7,055 | 4,990 | 2,750 | 2,225 | 1,215 |
| Sep 2026 | 7,780 | 6,855 | 5,000 | 3,030 | 2,480 | 1,225 |
| Oct 2026 | 8,210 | 6,100 | 4,820 | 2,945 | 2,050 | 915 |
| Twelve months | 97,020 | 84,155 | 51,715 | about 27,500 | about 20,500 | about 13,600 |
Source: DSS, Inclusive Employment Australia monthly profile, 31 October 2026 edition, tabs g (Flow Data) and j (Outcomes Data). Flow totals are the workbook’s own Table 4 totals on tab f. The workbook gives no total row for outcomes, so the twelve-month outcome figures are our sums of rounded cells, shown to the nearest 100 (see Methodology). Every cell is rounded to the nearest 5 by the department.
The flows are steady and unremarkable: between 5,900 and 9,700 referrals a month, and a caseload that grew by 14,715, about 6 per cent, from the first published count at 30 November 2025. The outcome columns are where the year has a shape. Twelve-week outcomes ran between 925 and 2,130 a month from November to April, then 3,040 in May and between 2,750 and 3,030 in every month since. Averaged, that is about 1,650 a month before May and about 2,930 after, a rise of about three-quarters. Twenty-six-week outcomes did nothing comparable until August, when they went from 1,490 to 2,225, and they have stayed above 2,000.
Which outcomes can belong to the new program
The workbook defines all three outcomes the same way: a participant is in paid employment and maintains that employment over a defined period, meeting the required Benchmark Hours (full or partial).
It also says, plainly, that people carried over from the old program count:
IEA transition participants as at 01-Nov-2025, who were already tracking to an outcome and achieved the outcome in IEA are included.
And it counts an outcome in the month its payment claim was created, which can only be after the
period is served B.
Exhibit B · from the source
Inclusive Employment Australia (IEA) replaced the Disability Employment Services (DES) program on November 1, 2025.
IEA Outcome counts are based on when payments for Outcomes were created, zero dollar payments (where value is less than $0.10) are excluded.
the earliest date for the rolling period is when IEAstarted on 01-Nov-2025
IEA transition participants as at 01-Nov-2025, who were already tracking to an outcome and achieved the outcome in IEA are included.
a participant is in paid employment and maintains that employment over a defined period, meeting the required Benchmark Hours (full or partial).
Put those together with a calendar and the year sorts itself. A job has to be held for 52 weeks before a 52-week outcome can be claimed, and 52 weeks before 31 October 2026 is 1 November 2025, the program’s first day. So every 52-week outcome in the year, about 13,600 of them, rests on a job that began on that first day or earlier. The same arithmetic covers the 26-week outcomes claimed from November to April, 9,490 of the year’s 20,500 or so, and the 2,675 twelve-week outcomes claimed in November and December.
Exhibit A · the cells and the date arithmetic
| Input | Value | Where |
|---|---|---|
| Program start | 1 November 2025 | Information tab, caveats |
| Rolling 12-month 52-week outcomes, by gender | 6,430 + 7,100 + 60 | Tab i, Table 1 |
| 26-week outcomes, Nov 2025 to Apr 2026 | 910, 1,425, 1,855, 1,710, 2,080, 1,510 | Tab j |
| 12-week outcomes, Apr and May 2026 | 2,130 and 3,040 | Tab j |
| 26-week outcomes, Jul and Aug 2026 | 1,490 and 2,225 | Tab j |
The arithmetic. 31 October 2026 less 52 weeks (364 days) is 1 November 2025. 30 April 2026 less 26 weeks is 30 October 2025, before the program began. 31 December 2025 less 12 weeks is 8 October 2025. 6,430 + 7,100 + 60 is 13,590 52-week outcomes. The six 26-week months sum to 9,490, 46% of the 20,455 in tab j. 3,040 over 2,130 is a rise of 43%; 2,225 over 1,490 is 49%. The gap between a 12-week and a 26-week milestone in the same job is 14 weeks; May to August is three months.
That gives the two steps a reading worth taking seriously. A job that reached twelve weeks in May started around February, inside the new program, and if it lasted it reached twenty-six weeks around August. The 26-week step arrived exactly where those jobs would put it, and was of similar size. That is consistent with a cohort of jobs found under the new program moving through the milestones. It is not proof. May is also the first edition in which the department published outcomes at all, and a step in claims can come from how claims are lodged as well as from how many people are in work. The workbook does not say which.
Updated 16 November 2026. We first wrote that the department’s site refused our requests for its servicing guidelines. Our requests early on 16 November did get refusals, but the same documents came through later that day, and we have now read Part B of the guidelines. It confirms the caveat in our method note: an outcome period can be broken by permissible breaks, generally up to 28 days in each stretch, which could put a job’s start earlier than our bound, never later. We changed this paragraph and the method note; the figures and the conclusion are unchanged.
What the year does not change
A quarter of the caseload is still recorded as suspended: 67,755 people, 26.0% at 31
October, against 25.5% in June. It is still one category. The glossary still says a participant
may be suspended for a variety of reasons, including part-time work, temporary incapacity to work and major personal crisis.
Working part-time and being in crisis remain indistinguishable in the published record. And the
monthly exit figures keep being restated after first publication, which we have
tracked edition by edition; the outcome
figures move too, if less, with September’s twelve-week figure going from 2,985 to 3,030
between the September and October editions.
Our view
The department deserves credit for what this workbook now is: twelve months of monthly outcome counts, broken down by disability, age and cohort, published for free with a plain statement that transition participants are counted.
But the claim a reader most wants tested, whether the new program gets people into lasting work better than the old one, still cannot be tested from it, and the reason is now precise. The 52-week figure, the one that measures a job lasting a year, is in its entirety a measure of jobs that began on or before the program’s first day. The twelve-week step in May is the most encouraging thing in the file, and the 26-week step in August is the first sign it may be real. The department could settle the question with one extra column: outcomes split by whether the job began before or after 1 November 2025. Until it does, the honest test date is the edition covering February 2027, when jobs that reached twelve weeks in May could first reach 52.
We will read the February 2027 edition when it is published and report whether 52-week outcomes made the same step that twelve-week outcomes made in May.